Article 6 of 9 · PMWEB for Contractors and Subcontractors

Both Sides of Every Contract

By , PMP, PSP, EVP, GPM · CEO & Chairman, CMCS FZCO

A contractor sits between two sets of contracts. Above it is the client, who pays late and disputes variations. Below it are subcontractors and suppliers, who expect to be paid on time and claim for every change. A contractor that manages these two sides in separate spreadsheets is always reconciling, and always one step behind its cash.

This article shows how PMWEB manages both sides of every contract in one project record: the Prime Contract with the client, and the Commitments with subcontractors, suppliers and internal units, with change orders, progress invoices, payments and funding connected throughout.

Figure 1. Both sides of every contract, in one place
Figure 1. Both sides of every contract, in one place

The Income Side: Prime Contract

The Prime Contract holds the schedule of values created from the selling price (Part 3), with the contract's terms: advance payment, retention, recovery of advance, payment period, bonds and liquidated damages. Against it the contractor records:

  • Change orders claimed from the client, with their status from potential to submitted to approved.
  • Progress invoices in the client's required format, generated from the approved progress on the schedule of values.
  • Payments received, matched to invoices, with retention held and the days each certificate was outstanding.
Figure 2. PMWEB 2026 progress invoice against the prime contract schedule of values
Figure 2. PMWEB 2026 progress invoice against the prime contract schedule of values

The Cost Side: Commitments

Every subcontract and purchase order awarded in Part 4, and every internal commitment from Part 5, is a Commitment in PMWEB. Against each, the contractor administers the full subcontract life cycle:

ProcessWhat PMWEB controlsWhy it matters
Change ordersSubcontractor variations approved within delegated limits and linked to the budgetNo variation is paid unless it is approved and funded
DisputesClaims and disputes logged with value, status, correspondence and decisionsThe company sees its exposure before it becomes a dispute it cannot settle
Interim paymentsSubcontractor applications checked against progress, retention and back-chargesOverpayment and premature release of retention are prevented
PaymentsPayments made, recorded against each applicationPaid-to-date always reconciles with certified-to-date
Figure 3. Subcontractor application and certificate for payment generated by PMWEB
Figure 3. Subcontractor application and certificate for payment generated by PMWEB

Back-to-Back, Side by Side

Because both sides are on the same cost codes, PMWEB shows each prime contract change order beside the subcontract change orders it generates, and each client payment beside the subcontractor payments it funds. The contractor sees immediately when it has approved a subcontractor variation that the client has not yet approved, or paid subcontractors faster than the client has paid it.

Figure 4. Contract performance dashboard: contract values, change orders, invoiced, paid and outstanding
Figure 4. Contract performance dashboard: contract values, change orders, invoiced, paid and outstanding
Figure 5. Change orders by status, type and cost
Figure 5. Change orders by status, type and cost

Cash, Funding and Bank Facilities

Fast-growing contractors run on bank facilities: overdrafts, project finance, letters of credit and guarantees. PMWEB's Funding module records each facility and its allocation to projects, so management can see how each project's cash gap is financed and how much headroom remains.

Figure 6. Funding recap: sources and amounts allocated against each project
Figure 6. Funding recap: sources and amounts allocated against each project
Figure 7. The cash gap on a project and how bank facilities close it
Figure 7. The cash gap on a project and how bank facilities close it
Figure 8. Delayed payments and interest charges by employer
Figure 8. Delayed payments and interest charges by employer

Delayed client payments are tracked with the interest or finance cost they create, giving the commercial team the evidence it needs to claim, and the bank the visibility it needs to keep supporting the business.

The Subcontractor's View

For a specialist subcontractor, the received subcontract is its prime contract. Every variation it claims from the main contractor, every application it submits and every payment it receives is tracked in PMWEB as income, while its own suppliers and sub-subcontractors are its commitments. Delayed payments from main contractors are the subcontractor's biggest risk; PMWEB makes them visible per main contractor and per project.

Where AI Adds Value

PMWEB 2026 AI can answer the questions finance directors ask every week: "Which subcontractor variations have we approved that are not yet approved by the client?", "Which clients are paying beyond their contract terms, and what is it costing us?", "What is the total of open commitment change orders on this project?"

Key takeaway

Contractors and subcontractors live between two sets of contracts. PMWEB manages both in one project record, so every change, invoice and payment on one side is visible against the other, back-to-back exposure is caught early, and cash, funding and delayed payments are visible live, not at month-end.

Next in the series, Part 7: Early Warning and Risk. Building a culture where everyone reports problems while there is still time to act.

Bassam Samman
Bassam Samman, PMP, PSP, EVP, GPM, is CEO and Chairman of CMCS FZCO, the PMWEB Authorized Implementation Partner for the GCC and MENA and PMWEB Global Partner of the Year 2025. He has more than 40 years of capital project experience, is a co-founder of the PMI Arabian Gulf Chapter and the author of four books on digitalising project delivery.

Next step

Bring this to your portfolio.

Tell us which processes matter most to you, and we will show them running in PMWEB.